None
Last 25 builds Last 7 days Last 30 days Last 90 days All builds

Recent plan failures

Failed In Fixed In Time Taken To Fix
#4126 Scheduled

#4133 Scheduled

7 builds

1 week, 23 minutes

#4123 Scheduled

#4125 Scheduled

2 builds

2 days, 1 minute

  • Average time to fix a failure: 4 days, 12 hours, 12 minutes
  • Average number of builds between fixes: 4.5 builds
  • The longest time taken to fix a failure is 1 week, 23 minutes, from failure starting in build #4126.
  • The greatest number of builds taken to fix a failure is 7, from failure starting in build #4126.